Rt. 400 Bridge, East Aurora, New York

Rt. 400 3
Rt 400
Rt 400 4
Rt 400 2

Project Location: East Aurora, New York

Project Highlights: 

  • Demolished a 136’ cast-in-place post-tension bridge between two bridge spans.
  • High-reach and hammer-equipped excavators were utilized for the demolition.
  • The entire project spanned a week in duration.
  • The demolition culminated in a 33-foot drop of the remaining structure while preserving the piers.
We have the experience to solve your bridge demolition challenges.