RFK Triborough Bridge Bronx Plaza, New York, New York

Img 0415

Project Location: New York, New York

Project Highlights:

  • Removed over 350,000 square feet of bridge structure.
  • Removed over 20,000 tons of concrete and 3,700 tons of steel.
  • 320 bridge girders were picked, and over 3,7000 tons of steel cross beams, stringers, and girders were removed through 15 lanes of traffic.
  • Bridge system that connects Manhattan, Queens, and the Bronx and sees an average daily traffic load of nearly 200,000 vehicles.
  • Project-wide change order called for the elimination of the toll booth system and conversion to Open Road Tolling, expedited efforts still brought the job in a year ahead of schedule.

 

We have the experience to solve your bridge demolition challenges.