Pearl Harbor Memorial Bridge, New Haven, Connecticut
We’re feeling a little nostalgic, so we’re throwing it back for a special Way Back Wrecking Wednesday!
This week, we’re spotlighting the demolition of the Pearl Harbor Memorial Bridge over the Quinnipiac River in New Haven, Connecticut. This was one of our more technical bridge demolition projects to date!
Sessler Wrecking was tasked with demolishing and removing 10,000 cubic yards of concrete substructure, with half of the material submerged at depths exceeding 30 feet. The project also included the removal of 170,000 square feet of concrete decking.
Working from trestles and barges, our crews utilized Trimble 3D guidance systems to maintain accuracy and control throughout the underwater demolition process.
The scale and complexity of this project showcased the specialized expertise, marine equipment, and advanced technology Sessler brings to challenging demolition work above and below the waterline.